NO | PROJECT | CLIENT | DESCRIPTION | QTY(Ton) | Delivery | Country | Remarks |
---|---|---|---|---|---|---|---|
1 | LONG-PHU #1 | Power Machines | CS / ALLOY (P11, P91) Hanger & Supports 1,600 sets / 380 tons | 3532 | On Going | VIETNAM | 1,200MW (600MW x 2Units) |
2 | Hsinta | GE Power | CS / SS / ALLOY (P11, P22, P91, P92) | 1360 | On Going | TAIWAN | 2,580MW (430MW x 6Units) |
3 | Hsinta | GE Power | CS / SS / ALLOY (P22, P91, P92) | 5136 | On Going | TAIWAN | 3,900MW (1,300MW x 3Units) |
4 | Hsinta | GE Power | CS / SS | 26.96 | On Going | USA | 3,900MW (1,300MW x 3Units) |
5 | TVA Colbert | GE Power | CS / SS | 53.38 | On Going | USA | 717MW (239MW x 3Units) |
6 | TVA Paradise | GE Power | CS / SS | 39.84 | On Going | USA | 717MW (239MW x 3Units) |
7 | Tongyeong | GE Power | CS / SS | 2.2 | On Going | KOREA | 1012MW (506MW x 2Units) |
8 | Taichung | GE Power | CS / SS / ALLOY (P11, P22, P91, P92) | 129 | On Going | TAIWAN | 5500MW (1,375MW x 4 Units) |
9 | Taichung MSD | GE Power | CS / SS / ALLOY | 21.06 | On Going | TAIWAN | 2600 MW (1300 MW x 2 Units) |
10 | Mansinloc | Mitsubishi Power (Nagasaki) | CS / ALLOY (P11, P12) | 196 | On Going | PHILIPPINES | 630 MW (315 MW x 2 Units) |
11 | Taichung | GE Power | CS / SS / ALLOY (P22, P91, P92) | 3317 | On Going | TAIWAN | 2600 MW (1300 MW x 2 Units) |
12 | Mansinloc | Mitsubishi Power (Hitachi) | CS / SS / ALLOY (P11, P22, P91) | 132.3 | On Going | PHILIPPINES | 630 MW (315 MW x 2 Units) |
13 | UTE Novo Temp Barcarena Project | Mitsubishi Power (Takasago) | CS / SS / ALLOY (P11, P22, P91) | 10.4 | On Going | BRAZIL | 605 MW (605 MW X 1 Unit) |
14 | Dah tarn Stage-2 Plant | Mitsubishi Power (Takasago) | CS / SS / ALLOY (P22) | 29.17 | On Going | TAIWAN | 1446 MW (723 MW X 2 Units) |
15 | EDF Luminus Seraing | GE Power | CS / SS / ALLOY (P11, P22, P91, P92) | 294 | On Going | Belgium | 870 MW (870 MW X 1 Unit) |
16 | Plaquemines -2 | GE Power | CS / SS / ALLOY (P11, P22, P91) -Valve Shop Installation (MOV Valve 30 ea / 5 tons Manual Valve 155 ea / 51 tons) | 490 | On Going | USA | 987 MW (987 MW x 1 Unit) |
17 | Hsinta CW Piping | GE Power | SS | 428 | On Going | TAIWAN | 3,900MW (1,300MW x 3Units) |
18 | Taichung CW Piping | GE Power | SS | 278 | On Going | TAIWAN | 2600 MW (1300 MW x 2 Units) |
19 | Luminus Seraing MSD | GE Power | CS / SS | 3.428 | On Going | BELGIUM | 870 MW (870 MW X 1 Unit) |
20 | Entergy Orange County | Mitsubishi Power (Takasago) | CS / SS / ALLOY (P11, P22, P91) | 30 | On Going | USA | 1215 MW (607 MW x 2 Units) |
21 | Magnolia Kindle HRSG | GE Power | CS / SS / ALLOY (P11, P22, P91) -Valve Shop Installation | 20 | On Going | USA | 700 MW (700 MW X 1 Unit) |
22 | Bucheon MSD | GE Power | SS | 0.91642717832 | On Going | KOREA | 450 MW (450 MW X 1 Unit) |
23 | Azulao MSD | GE Power | CS / SS | 2.236 | On Going | BRAZIL | 590MW (295 MW X 2 Units) |
24 | Shady Hills | GE Power | CS / SS / ALLOY (P11, P22, P91, P92) -Valve Shop Installation | 232 | On Going | USA | 541 MW (541 MW X 1Unit) |
25 | CenterPoint MSD | GE Power | CS / SS | 18.555358219 | On Going | USA | 460MW (230 MW X 2 Units) |
26 | VERBENA MSD | GE Power | SS | 1.558 | On Going | TURKEY | 850 MW (850 MW X 1 Unit) |
27 | Meranti | Mitsubishi Power (Hitachi) | CS / SS | 12 | On Going | SINGAPORE | 680 MW (680 MW x1 Unit) |
28 | Hsintao MSD | GE Power | SS | 7.5 | On Going | TAIWAN | 600 MW (600 MW X 1 Unit) |
29 | XCEL Wheaton MSD | GE Power | CS / SS | 5.831 | On Going | USA | 430 MW (430 MW X 1 Unit) |
30 | Jafurah Cogen MSD | GE Power | CS / SS | 2.1372568323 | On Going | SAUDI ARABIA | 320 MW (320 MW X 1 Unit) |
31 | GUMI | Mitsubishi Power (Takasago) | CS / SS / ALLOY (P11, P12, P22) | 82 | On Going | KOREA | 500 MW (500 MW x1 Unit) |
32 | TVA Cumberland | GE Power | CS / ALLOY (P11, P22, P91, P92) | 282 | On Going | USA | 1450 MW (1450 MW X 1Unit) |
33 | Chung Chia | GE Power | CS / SS / ALLOY (P11, P22, P91, P92) | 22 | On Going | TAIWAN | 610 MW (610 MW X 1 Unit) |
34 | Verbena | GE Power | CS / SS / ALLOY (P11, P22, P91, P92) | 4.2 | On Going | Turkey | 850 MW (850 MW X 1Unit) |
35 | KEPPEL | Mitsubishi Power (Takasago) | CS / SS / ALLOY (P22, P91) | 19 | On Going | SINGAPORE | 600 MW (600 MW x1 Unit) |
36 | Altbach | GE Power | EN MATERIAL (CS, SS, ALLOY) | 158 | On Going | GERMANY | 680 MW (680 MW X 1Unit) |
37 | Heilbronn | GE Power | EN MATERIAL (CS, SS, ALLOY) | 158 | On Going | GERMANY | 680 MW (680 MW X 1Unit) |
38 | ORANGE | BORSIG | CS | 582 | On Going | USA | 1215 MW (607 MW x 2 Units) |
39 | NAEPO | GE Power | CS / SS / ALLOY (P11, P22, P91, P92) | 50 | 2022.11 | KOREA | 555MW (555MW x 1Unit) |
40 | Tallawarra B | GE Power | SS | 3 | 2022.10 | Austraila | 316 MW (316MW X 1 Unit) |
41 | Fujairah F3 IPP Unit 1, 2, 3 | Mitsubishi Power (Hitachi) | CS / SS | 19 | 2021.12 | UAE | 2,400MW (800MW x 3Units) |
42 | LAMMA 12 | Mitsubishi Power (Kure) | CS / SS / ALLOY (P11, P12, P22) | 190.1 | 2021.12 | HONG KONG | 380MW (380MW x 1Unit) |
43 | SAIJO Unit 1 | Mitsubishi Power (Hitachi) | CS / SS | 191 | 2021.11 | JAPAN | 500MW (500MW x 1Unit) |
44 | SAIJO Unit 1 | Mitsubishi Power (Hitachi) | CS | 87 | 2021.11 | JAPAN | 500MW (500MW x 1Unit) |
45 | Fujairah F3 IPP Unit 1, 2, 3 | BHI | CS / ALLOY (P11, P22, P91, P92) | 654 | 2021.10 | UAE | 2,400MW (800MW x 3Units) |
46 | NAEPO | GE Power | CS / SS | 1.3 | 2021.10 | KOREA | 555MW (555MW x 1Unit) |
47 | Power South Lowman Energy Center | Mitsubishi Power (Hitachi) | CS / SS / ALLOY (P91) | 16 | 2021.07 | USA | 640MW (320MW x 2Units) |
48 | Dania Beach | GE Power | CS / SS | 14.25 | 2021.03 | USA | 1,163MW (580MW x 2Units) |
49 | Al Dur IWPP | BHI | CS / SS / ALLOY (P11, P22, P91) | 428 | 2020.11 | BAHRAIN | 1,500MW |
50 | RDMP RU-V Balikpapan | BHI | CS / ALLOY (P11, P12) | 58 | 2020.11 | INDONESIA | 20MW |
51 | TOKUYAMA UNIT.3 | Mitsubishi Power (Hitachi) | CS / SS | 452 | 2020.10 | JAPAN | 300MW (300MW x 1Unit) |
52 | JACKSON | Mitsubishi Power (Hitachi) | CS / SS / ALLOY (P11, P91) | 43 | 2020.10 | USA | 1,200MW (600MW x 2Units) |
53 | TAKETOYO No.5 | Mitsubishi Power (Hitachi) | CS / SS | 551 | 2020.08 | JAPAN | 1,070MW (1,070MW x 1Unit) |
54 | Shinsejong | GE Power | CS / ALLOY (P11, P22, P92) | 326 | 202212 | KOREA | 530MW (530MW x 1Unit) |
55 | Silverhawk MSD | GE Power | SS | 7.09235890352 | 2023-11-09 | USA | 520 MW (260 MW X 2 Units) |
56 | Plaquemines MSD | GE Power | SS | 22 | 2023-11-02 | USA | 987 MW (987 MW x 1 Unit) |
57 | MAGNOLIA MSD | GE Power | CS / SS | 3.2895612379 | 2023-09-20 | USA | 323 MW (323 MW X 1 Unit) |
58 | Besmaya MSD | GE Power | CS / SS | 2.08 | 2023-08-09 | IRAQ | 1,500MW (1,500MW x 1 Unit) |
59 | MANZANILLO MSD | GE Power | SS | 0.122 | 2023-07-27 | MEXICO | 700 MW (700 MW X 1 Unit) |
60 | Tanajib MSD | GE Power | CS / SS | 10.14 | 2023-06-22 | SAUDI ARABIA | 5500MW (1,375MW x 4 Units) |
61 | Panama MSD | GE Power | CS / SS | 11.98 | 2023-03-23 | PANAMA | 670 MW (335 MW X 2 Units) |
62 | Shinsejong MSD | GE Power | CS / SS | 9.06 | 2023-03-06 | KOREA | 630 MW (630 MWx 1 Unit) |
63 | Tepco Goi | GE Power | CS / SS / KA / ALLOY (P11, P22) | 820 | 2023.11 | JAPAN | 2,340MW (780MW x 3 units) |
64 | Merida Project | Mitsubishi Power (Hitachi) | CS / SS / ALLOY (P11, P22, P91) | 36 | 2023.08 | MEXICO | 532 MW (532 MW x 1 Unit) |
65 | Plaquemines | GE Power | CS / SS / ALLOY (P11, P22, P91) -Valve Shop Installation (MOV Valve 30 ea / 5 tons Manual Valve 155 ea / 51 tons) | 490 | 2023.08 | USA | 987 MW (987 MW x 1 Unit) |
66 | JAWA 9 & 10 | SIEMENS | CS / SS / ALLOY (P11, P22, P91, P92) | 387.2 | 2023.07 | INDONESIA | 2000 MW (1000 MW x 2 Units) |
67 | Tongyeong | GE Power | CS / SS / ALLOY (P22, P91, P92) | 97 | 2023.07 | KOREA | 1012MW (506MW x 2Units) |
68 | Daegu Cheongju | Mitsubishi Power (Takasago) | CS / SS / ALLOY (P11, P12, P22) | 148 | 2023.06 | KOREA | 540MW (270MW x 2Units) |
69 | Valladolid | Mitsubishi Power (Hitachi) | CS / SS / ALLOY (P11, P22, P91) | 35 | 2023.06 | MEXICO | 525 MW (525 MW X 1 Units) |
70 | Intermountain Power | Mitsubishi Power (Hitachi) | CS / SS / ALLOY (P11, P22, P91) | 34.5 | 2023.05 | USA | 1640 MW (820 x 2 Units) |
71 | Ostroleka | GE Power | CS / ALLOY (P11, P22, P91) / SS | 263 | 2023.05 | POLAND | 750 MW (75 MW X 1 Unit) |
72 | Bazian | GE Power | CS / SS / ALLOY (P22) | 297 | 2023.04 | IRAQ | 500 MW (125 MW x 4 Units) |
73 | Gulf Pluak Daeng | Mitsubishi Power (Hitachi) | CS / SS / ALLOY (P22, P91) | 72.6 | 2023.03 | THAILAND | 2,650MW (660MW x 4Units) |
74 | Oumache III | BHI | CS / SS / ALLOY (P11, P22, P91) | 972 | 2023.03 | ALGERIA | 1,300MW (4Units) |
75 | HinKong | Mitsubishi Power (Hitachi) | CS / SS / ALLOY (P91) | 74.69 | 2023.03 | THAILAND | 1400MW (700MW x 2Units) |
76 | Ukudu IPP Project | BHI | CS / SS / ALLOY (P11, P22, P91) | 121 | 2023.03 | USA | 180 MW (180 MW x 1 Unit) |
77 | PANAMA | GE Power | CS / SS / ALLOY (P11, P22, P91) | 234 | 2023.03 | PANAMA | 670 MW (335 MW X 2 Units) |
78 | Tanajib | BHI | CS / SS / ALLOY (P11, P22, P91) | 300 | 2023.03 | SAUDI ARABIA | 940 MW (940 MW X 1 Unit) |
79 | SK MU Internal Piping | BHI | CS / SS / ALLOY (P11, P22, P91) | 85.8 | 2023.03 | KOREA | 300 MW (300MW X 1 Unit) |
80 | Saudi Arabia GCC Project | Mitsubishi Power (Hitachi) | CS / ALLOY (P12) | 35 | 2023.02 | SAUDI ARABIA | - |
81 | HinKong | BHI | CS / ALLOY (P11, P22, P91) | 428.3 | 2023.01 | THAILAND | 1400MW (700MW x 2Units) |
82 | Hin Kong | BHI | CS / SS / ALLOY (P11, P22, P91) | 320 | 2023.01 | THAILAND | 1400MW (700MW x 2Units) |
83 | Tongyeong | GE Power | ALLOY (P11, P22, P91, P92) | 529 | 2022.11 | KOREA | 1,012MW (506MW x 2Units) |
84 | Black Point D2 | BHI | CS / SS / ALLOY (P11, P22, P91, P92) | 991 | 2022.11 | HONG KONG | 600MW (600MW x 1Unit) |
85 | Pulau Indah | GE Power | CS / SS / ALLOY (P22, P91, P92) | 76.65 | 2022.11 | MALAYSIA | 1200MW (600MW x 2 Units) |
86 | Salamanca | Mitsubishi Power (Hitachi) | CS / SS / ALLOY (P11, P22, P91) | 22.628 | 2022.11 | MEXICO | 1400MW (700MW x 2Units) |
87 | JERA ANEGASAKI | Mitsubishi Power (Hitachi) | CS / SS / ALLOY (P22) | 12.5 | 2022.09 | JAPAN | 1,950MW (650MW x 3Units) |
88 | DATAN Unit 7 | Mitsubishi Power (Hitachi) | CS / SS / ALLOY (P11, P22, P91) | 35.19 | 2022.09 | TAIWAN | 600MW (600MW x 1Unit) |
89 | LAMMA 12 | Mitsubishi Power (Takasago) | CS / SS / ALLOY (P11, P22, P91) | 367.7 | 2022.08 | HONG KONG | 380MW (380MW x 1Unit) |
90 | DATAN Unit 8&9 | GE Power | SS / ALLOY (P22, P91, P92) | 2269 | 2022.07 | TAIWAN | 2,000MW (1,000MW x 2Units) |
91 | Meghnaghat | SAMSUNG C&T | CS / SS / ALLOY (P11, P22, P91) | 664.8 | 2022.06 | BANGLADESH | 718MW (718MW x 1Unit) |
92 | NAEPO | GE Power | CS / SS / ALLOY (P11, P22, P91, P92) | 237 | 2022.06 | KOREA | 500MW (500MW x 1Unit) |
93 | Thai Oil CFP Boiler | Hyundai Heavy Industries Power System | CS / ALLOY (P11, P22, P91) | 413.3 | 2022.05 | THAILAND | 250MW (260MW x 1Unit) |
94 | JERA ANEGASAKI | Mitsubishi Power (Takasago) | CS / SS / ALLOY (P11, P22) | 587.8 | 2022.05 | JAPAN | 1,950MW (650MW x 3Units) |
95 | BARRY 8 Expansion | Mitsubishi Power (Hitachi) | CS / SS / ALLOY (P91) | 31 | 2022.05 | USA | 720MW (720MW x 1Unit) |
96 | Sarawak | BHI | CS / SS / ALLOY (P11, P12, P22) | 67 | 2022.04 | MALAYSIA | - |
97 | Dolna Odra | GE Power | CS / SS / ALLOY (P11, P22, P91, P92) | 494 | 2022.03 | POLAND | 1,400MW (700MW x 2Units) |
98 | Starbuck | GE Power | CS / SS / ALLOY (P11, P22, P91) | 113 | 2022.02 | TAIWAN | 490MW (490MW x 1Unit) |
99 | CPV Three River | GE Power | CS / SS | 23.06 | 2021.09 | USA | 1,250MW (625MW x 2Units) |
100 | DATAN Unit 8&9 | GE Power | CS / ALLOY (P11, P22, P91, P92) | 1099 | 2021.05 | TAIWAN | 1,536MW (384MW x 4Units) |
101 | UNIQUE | GE Power | CS / SS / ALLOY (P11, P22, P91, P92) | 222 | 2021.05 | BANGLADESH | 584MW (584MW x 1Unit) |
102 | Colombia Termocandelaria Bottoming Cycle | Mitsubishi Power (Hitachi) | CS / SS / ALLOY (P11, P22, P91) | 12 | 2021.04 | COLOMBIA | 566MW (566MW x 1Unit) |
103 | Marlim Azul | Mitsubishi Power (Hitachi) | CS / SS / ALLOY (P91) | 11 | 2021.03 | BRAZIL | 565MW (565MW x 1Unit) |
104 | Mexico Tamanunchale II | Mitsubishi Power (Hitachi) | CS / SS / ALLOY (P22, P91) | 13 | 2021.03 | MEXICO | 560MW (560MW x 1Unit) |
105 | NSK | TURBODEN | CS | 43 | 2021.02 | CANADA | 8.4 MW (8.4MW x 1Unit) |
106 | Long Ridge (Hannibal) | GE Power | CS / SS / ALLOY (P11, P22, P91, P92) -Valve Shop Installation (MOV Valve 25 ea / 8.4 tons Manual Valve 550 ea / 18 tons ) | 218 | 2021.01 | USA | 485MW (485MW x 1Unit) |
107 | Guernsey | GE Power | CS / SS / ALLOY (P11, P22, P91, P92) -Valve Shop Installation (MOV Valve 69 ea / 3 tons Manual Valve 1,224 ea / 10.8 tons) | 55 | 2020.11 | USA | 1,875MW (625MW x 3Units) |
108 | AZITO IV | GE Power | CS / SS / ALLOY (P11, P22) | 103 | 2020.11 | IVORY COAST | 710MW (710MW x 1Unit) |
109 | SEWA HAMRIYAH IPP | GE Power | CS / SS / ALLOY (P11, P22, P91, P92) | 740 | 2020.08 | UAE | 1,800MW (600MW x 3Units) |
110 | Nghi Son 2 | Mitsubishi Power (Hitachi) | CS / SS / ALLOY (P11, P22, P91) | 250 | 2020.07 | Vietnam | 1,330MW (665MW x 2Uits) |
111 | JAWA-1 | SAMSUNG C&T | CS / ALLOY (P11, P91, P92) | 1417 | 2020.07 | INDONESIA | 1,760MW (880MW x 2Units) |
112 | CHIAHUI Phase2 EXPANSION | GE Power | CS / SS / ALLOY (P22, P91, P92) | 421 | 2020.06 | TAIWAN | 670MW (670MW x 1Unit) |
113 | ORC PLANT LAG C/S PIPING | TURBODEN | CS | 57 | 2020.06 | EL SALVADOR | 204MW |
114 | GSRC Gulf Sriracha | Mitsubishi Power (Hitachi) | CS / SS / ALLOY (P22, P91) | 75 | 2020.05 | THAILAND | 2,500MW (625MW x 4Units) |
115 | Al Layyah | Mitsubishi Power (Hitachi) | CS / SS / ALLOY (P91) | 45 | 2020.04 | UAE | 1,026MW (566MW x 2Units) |
116 | NAM-JEJU | DAEWOO E&C | CS / SS / ALLOY (P22, P91) | 310 | 2020.04 | KOREA | 100MW (100MW x 1Unit) |
117 | Kiewit Hill Top | GE Power | CS / ALLOY (P11, P22, P91, P92) -Valve Shop Installation (MOV Valve 16 ea / 9.8 tons Manual Valve 39 ea / 15 tons) | 288 | 2020.04 | USA | 620MW (620MW x 1Unit) |
118 | Riau IPP | GE Power | CS / SS / ALLOY (P11, P22, P91, P92) | 192 | 2020.03 | INDONESIA | 275MW (137MW x 2Units) |
119 | NNEG | BHI | CS / ALLOY (P11, P22) | 11 | 2020.01 | THAILAND | 60MW (1Unit) |
120 | Jawa-1 IPP | GE Power | CS / SS / ALLOY (P11, P22, P91, P92) | 801 | 2020.01 | INDONESIA | 1,760MW (880MW x 2Units) |
121 | Parnaiba | GE Power | CS / SS / ALLOY (P11, P22, P91, P92) | 480 | 2020.01 | BRAZIL | 1,820MW (364MW x 5Units) |
122 | GSRC Gulf Sriracha | NOOTER/ERIKSEN | CS -Valve Shop Installation (Manual Valve 284 ea, 6 tons) | 11 | 2019.12 | THAILAND | 2,500MW (625MW x 4Units) |
123 | Chia Hui Extension | GE Power | CS / SS / ALLOY (P11, P22, P91, P92) | 248 | 2019.11 | TAIWAN | 670MW (670MW x 1Unit) |
124 | ARAB POTASH LB | NOOTER/ERIKSEN | CS / ALLOY (P11, P22) | 12 | 2019.11 | JORDAN | - |
125 | SHIN SEOCHEON | DAELIM | CS / SS / ALLOY (P11, P12, P22, P91) | 1338 | 2019.06 | KOREA | 1,000MW (1,000MW x 1Unit) |
126 | Montgomery LB,SB | NOOTER/ERIKSEN | CS / SS / ALLOY (P11, P22, P91) -Valve Shop Installation (MOV Valve 82 ea, 33.7 tons Manual Valve 756 ea, 21.1 tons) | 519 | 2019.06 | USA | 993MW (496MW x 2Units) |
127 | SHIN SEOCHEON | KOMIPO | CS / SS / ALLOY (P11, P12, P92) Hanger & Support 870 sets / 190 tons | 1620 | 2019.05 | KOREA | 1,000MW (1,000MW x 1Unit) |
128 | Melaka | GE Power | CS / ALLOY (P11, P22, P91, P92) | 874 | 2019.05 | MALAYSIA | 2,242MW (747MW x 3Units) |
129 | Tambak Lorok Block 3 | GE Power | CS / ALLOY (P11, P22, P91, P92) | 253 | 2019.04 | INDONESIA | 780MW (780MW x 1Unit) |
130 | Beer Tuvia | GE Power | CS / SS / ALLOY (P11, P22, P91) | 223 | 2019.03 | ISRAEL | 451MW (225.5MW x 2Units) |
131 | XTRC Rades-C | Mitsubishi Power (Hitachi) | CS / SS / ALLOY (P22, P91) | 17 | 2019.02 | TUNISIA | 450MW (450MW x 1Unit) |
132 | Muara Karang LB PIPING | NOOTER/ERIKSEN | CS / SS / ALLOY (P11, P22, P91) -Valve Shop Installation (MOV Valve 2 ea / 0.6 tons) | 240 | 2018.12 | INDONESIA | 500MW (500MW x 1Unit) |
133 | Shin pyeongtaek | Mitsubishi Power (Takasago) | CS | 19 | 2018.09 | KOREA | 950MW (950MW x 1Unit) |
134 | Lake charles LB,SB PIPING | NOOTER/ERIKSEN | CS / ALLOY (P11, P22, P91) -Valve Shop Installation (MOV Valve 78 ea / 23.8 tons Manual Valve 760 ea / 23 tons) | 524 | 2018.09 | USA | 980MW (490MW x 2Units) |
135 | UTE PORTO DE / SERGIPE | GE Power (Switzerland) | CS / SS | 267 | 2018.07 | BRAZIL | 1,551MW (380MW x 4Units) |
136 | UTE PORTO DE / SERGIPE | GE Power (Switzerland) | CS / SS | 64 | 2018.07 | BRAZIL | 1,551MW (380MW x 4Units) |
137 | MPP EXTERNAL SB PIPING (Moka Power Plant) | BHI | CS / SS / ALLOY (P11, P22) / KA(STPA28) | 48 | 2018.07 | JAPAN | 700MW (2Units) |
138 | MPP DTR EXTERNAL (Moka Power Plant) | BHI | CS | 31 | 2018.07 | JAPAN | 700MW (2Units) |
139 | MOKA | BHI | CS / ALLOY (P11, P22, P91) | 384 | 2018.06 | JAPAN | 700MW (2Units) |
140 | NAVOI | Mitsubishi Power (Hitachi) | CS / SS / ALLOY (P22, P91) | 26 | 2018.06 | UZBEKISTAN | 450MW (450MW x 1Unit) |
141 | TURAKURGAN | Mitsubishi Power (Hitachi) | ALLOY (P22) | 69 | 2018.06 | UZBEKISTAN | 900MW (450MW x 2Units) |
142 | Fadhili | DOOSAN | CS | 2242 | 2018.05 | SAUDI | 1,509 MW (301MW x 5Units) |
143 | Azzour South Third / EXTERNAL PIPING | BHI | CS / SS / ALLOY (P11, P22, P91) | 175 | 2018.05 | KUWAIT | 1,500MW (2Units) |
144 | Fadhili | GE Power | CS / SS / ALLOY (P22, P91) | 295 | 2018.04 | SAUDI | 1,509 MW (301MW x 5Units) |
145 | Shin-Pyeongtaek | GE Power | CS / SS / ALLOY (P11, P22, P91, P92) | 184 | 2018.04 | KOREA | 950MW (950MW x 1Unit) |
146 | Azzour South Third Internal PIPING | BHI | CS / ALLOY (P11, P22, P91) | 169 | 2018.02 | KUWAIT | 1,500MW (2Units) |
147 | RIVER SIDE LB PIPING | NOOTER/ERIKSEN | CS / SS / ALLOY (P22) | 44 | 2018.01 | USA | 650MW (300MW X 2Units) |
148 | BORYONG #7/8 3 Plant | KOMIPO | ALLOY (P92) | 3 | 2017.12 | KOREA | 1,000MW (500MW x 2Units) |
149 | MEGA MOSTAGHANEM | BHI | CS / ALLOY (P11, P22, P91) | 1040 | 2017.11 | ALGERIA | 1,450MW (362.5MW x4Units) |
150 | PANAMA COLON POWER PLANT | POSCO E&C | CS / SS / ALLOY (P11, P91) | 847 | 2017.11 | PANAMA | 391MW (391MW x 1Unit) |
151 | SAN BUENAVENTURA | Mitsubishi Power (Hitachi) | ALLOY (P91) | 22 | 2017.11 | PHILIPPINES | 500MW (500MW x 1Unit) |
152 | SAN BUENAVENTURA | Mitsubishi Power (Hitachi) | CS / SS / ALLOY (P11, P22, P91) | 80 | 2017.11 | PHILIPPINES | 500MW (500MW x 1Unit) |
153 | JEJU | GE Power | CS / SS / ALLOY (P11, P22, P91) | 91 | 2017.11 | KOREA | 240MW (120MW x 2Units) |
154 | RIVER SIDE SB PIPING | NOOTER/ERIKSEN | CS / ALLOY (P11, P12, P22, P91) | 30 | 2017.11 | USA | 650MW (300MW X 2Units) |
155 | ANYANG | BHI | CS / SS / ALLOY (P11, P22, P91, P92) | 341 | 2017.09 | KOREA | 450MW (2Units) |
156 | ISHIKARIWAN | GE Power | CS / ALLOY (P11, P22, P91) | 87 | 2017.08 | JAPAN | 569MW (569MW x 1Unit) |
157 | JIJEL | GE Power | CS / SS / ALLOY (P11, P22, P91) | 337 | 2017.07 | ALGERIA | 1,398MW (349.5MW x 4Units) |
158 | GRATI | GE Power | CS / SS / ALLOY (P22, P91) | 107 | 2017.07 | INDONESIA | 450MW (225MW x 2Units) |
159 | AYSEVEN | S&TC | CS / SS / ALLOY (P11, P22, P91) | 748 | 2017.05 | IRAN | 350MW (6Units) |
160 | ASSIUT | GE Power | CS / SS / ALLOY (P11, P12, P22) | 296 | 2017.04 | EGYPT | 1,000MW (125MW x 8Units) |
161 | BISKRA | HDEC | CS / SS / ALLOY (P11, P22, P91) | 3164 | 2017.04 | ALGERIA | 1,338MW (4Units) |
162 | JIJEL | HDEC | CS / SS / ALLOY (P11, P22, P91) | 3243 | 2017.04 | ALGERIA | 1,398MW (349.5MW x 4Units) |
163 | CLECO | BHI | CS / SS / ALLOY (P11, P22, P91, P92) | 51 | 2017.04 | USA | 50MW (50MW x 1Unit) |
164 | PANAMA COLON POWER PLANT | BHI | CS / ALLOY (P11, P22, P91) | 101 | 2017.04 | PANAMA | 380MW (126MW x 3Units) |
165 | UMM AL HOUL | NOOTER/ERIKSEN | CS / SS / ALLOY (P11, P22, P91) | 947 | 2017.04 | QATAR | 2,520MW (420MW x 6Units) |
166 | RED DRAGON (PIEM) | SK E&C | CS / ALLOY (P11, P22, P91) | 452 | 2017.03 | CHILE | 375MW (375MW x 1Unit) |
167 | KARBALA REFINERY | GS ENTEC | CS / SS / ALLOY (P11) | 186 | 2017.01 | IRAQ | 450MW (4Units) |
168 | SAFI | Mitsubishi Power (Hitachi) | ALLOY (P91) | 270 | 2017.01 | MOROCCO | 1386MW (693MW x 2Units) |
169 | SANTO DOMINGO | GE Power | CS / SS / ALLOY (P22, P91) | 60 | 2017.01 | DOMINICAN Rep | 145MW (145MW x 1Unit) |
170 | MAZANDARAN | BHI | CS / SS / ALLOY (P11, P22, P91) | 274.091 | 2017.01 | IRAN | 450MW (2Units) |
171 | MEGA NAAMA | BHI | CS / SS / ALLOY (P11, P22, P91) | 412 | 2016.12 | ALGERIA | 1,163MW (290MW x 4Units) |
172 | BISKRA | GE Power | CS / SS / ALLOY (P11, P22, P91) | 331 | 2016.11 | ALGERIA | 1,338MW (334.5MW x 4Units) |
173 | BANPONG | BHI | CS / SS / ALLOY (P11,22) | 72 | 2016.07 | THAILAND | 150MW (37.5MW x 4Units) |
174 | NGHI SON | NEM | CS / SS / ALLOY (P11, P22) | 91 | 2016.02 | VIETNAM | 1,200MW (600MW x 2Units) |
175 | JANGMOON | GS ENTEC | CS / SS / ALLOY (P11, P22, P91) | 918 | 2016.01 | KOREA | 950MW (4Units) |
176 | DANGJIN #4 | GS ENTEC | CS / SS / ALLOY (P11, P22, P91) | 321 | 2016.01 | KOREA | 950MW (2Units) |
177 | YORK II | BHI | CS / SS / ALLOY (P11, P22, P91) | 225 | 2015.12 | USA | 565MW (282MW x 2Units) |
178 | CHUNCHEON | BHI | CS / ALLOY (P11, P22, P91, P92) | 160 | 2015.12 | KOREA | 500MW (500MW x 1Unit) |
179 | MANJUN HP | Mitsubishi Power (Hitachi) | ALLOY (P92) | 38 | 2015.09 | MALAYSIA | 1,000MW (1,000MW x 1Unit) |
180 | SHIN-BORYUNG #1/2 | KOMIPO | CS / SS / ALLOY (P11, P12, P92) Hanger & Supports 1,600 sets / 380 tons | 3460 | 2015.08 | KOREA | 2,000MW (1,000MW X 2Units) |
181 | SAEMANGEUM #1/2 | DOOSAN / OCISE | CS / SS / ALLOY (P11, P22, P91) | 1338 | 2015.07 | KOREA | 303MW (150MW X 2Units) |
182 | AZ-ZOUR NORTH IWPP | HHI / PTB | CS / SS / ALLOY (P22, P91) | 551 | 2015.05 | KUWAIT | 1,500MW (1Unit) |
183 | LARA #1/2 | Mitsubishi Power (Hitachi) | CS / ALLOY (P22, P91) | 270 | 2014.12 | INDIA | 1,600MW (800MW x 2Units) |
184 | TRIPOLI #1/2/3/4 | Mitsubishi Power (Hitachi) | CS / SS / ALLOY (P11, P22) | 121 | 2014.09 | LIBYA | 1,400MW (350MW x 4Units) |
185 | SAMCHUK GREEN / POWER #1/2 | KOSPO | CS / SS / ALLOY (P11, P92) Hanger & Supports 1,600 sets / 380 tons | 3980 | 2014.07 | KOREA | 2,000MW (1,000MW x 2Units) |
186 | TIHAMA | HHI | CS / SS | 600 | 2014.06 | SAUDI | 1,595MW (1Unit) |
187 | SAMCHUK GREEN / POWER #1/2 | HDEC & GS | CS / SS / ALLOY (P11, P92) | 1800 | 2014.06 | KOREA | 2,000MW (1,000MW x 2Units) |
188 | CARMON CREEK | NEM | CS / ALLOY (P11, P22) | 477 | 2014.01 | CANADA | 630 MW (210MW x 3Units) |
189 | TAEAN #9/10 | Mitsubishi Power (Hitachi) | CS / SS / ALLOY (P91) | 515 | 2014.01 | KOREA | 2,000MW (1,000MW x 2Units) |
190 | BUKPYEONG #1/2 | Mitsubishi Power (Hitachi) | CS / SS / ALLOY (P91) | 355 | 2014.01 | KOREA | 1,190MW (595MW x 2Units) |
191 | ANSAN | POSCO E&C | CS / ALLOY (P11, P91) | 284 | 2013.12 | KOREA | 834MW (417MW x 2Units) |
192 | RABIGH #2 | DOOSAN | CS / SS / ALLOY (P22, P91) | 2050 | 2013.06 | SAUDI | 700MW (2Units) |
193 | RAIPUR | DOOSAN | CS / SS / ALLOY (P11, P22, P91) | 3300 | 2013.06 | INDIA | 685MW (685MW x 1Unit) |
194 | YEONGHEUNG #5/6 | DOOSAN | CS / SS / ALLOY (P11, P12, P22, P91, P92) | 2050 | 2013.06 | KOREA | 1,740MW (870MW x 2Units) |
195 | YANBU | DOOSAN | CS / SS / ALLOY (P22, P91) | 565 | 2013.05 | SAUDI | 690MW (690MW x 1Unit) |
196 | YEONGHEUNG #5/6 | KOEN | CS / SS / ALLOY (P11, P12, P22, P91, P92) Hanger & Support 1,750 sets / 390 tons | 1780 | 2013.03 | KOREA | 1,740MW (870MW x 2Units) |
197 | YEONGHEUNG #5/6 | Mitsubishi Power (Hitachi) | CS / SS / ALLOY (P11, P22, P91) | 390 | 2013.03 | KOREA | 1,740MW (870MW x 2Units) |
198 | EL AIN EL SOKHNA #1/2 | Mitsubishi Power (Hitachi) | CS / SS / ALLOY (P11, P22, P91) | 580 | 2012.03 | EGYPT | 1,300MW (650MW x 2Units) |
199 | OPC ROTEM | POSCO E&C | CS / SS / ALLOY (P11, P91) | 177 | 2012.03 | ISRAEL | 440MW (220MW x 2Units) |
200 | MARAFIQ #5/6 | DOOSAN | CS / SS / ALLOY (P11, P22, P91) | 490 | 2011.04 | SAUDI | 500MW (250MW x 2Units) |
201 | CIREBON #1 | DOOSAN | CS / SS / ALLOY (P11, P22, P91) | 2000 | 2011.02 | INDONESIA | 660MW (660MW x 1Unit) |
202 | SENOKO | Mitsubishi Power (Hitachi) | CS / SS / ALLOY (P11, P22, P91) | 162 | 2011.02 | SINGAPORE | 862MW (431MW x 2Units) |
203 | RIYADH PP11 IPP | HHI | CS / SS / ALLOY (P11, P22, P91) | 4500 | 2011.01 | SAUDI | 1,750MW (3Units) |
204 | SABIYA (COD) | HHI / MEW | ALLOY (P22, P91) | 922 | 2010.12 | KUWAIT | 1,320MW (2Units) |
205 | POSCO POWER LNG #5/6 | POSCO E&C | CS / SS / ALLOY (P11, P22, P91) | 850 | 2010.05 | KOREA | 500MW (2Units) |
206 | Angamos #1/2 | POSCO E&C | CS / SS / ALLOY (P22, P91) | 418 | 2010.04 | CHILE | 240MW (240MW x 1Unit) |
207 | MISURATA&BENGHAZI | DAEWOO E&C | CS / ALLOY (P11, P91) | 289 | 2010.02 | LIBYA | 750MW (250MW x 2Units) |
208 | ALKHALIJ #1/2/3/4 | Mitsubishi Power (Hitachi) | CS / SS / ALLOY (P11, P22, P91) | 120 | 2010.01 | LIBYA | 1,400MW (350MW x 4Units) |
209 | ARAK-SHAZAND | NEM | CS / ALLOY (P11, P22) | 120 | 2010.01 | IRAN | 1,300MW (650MW x 2Units) |
210 | Campiche | POSCO E&C | CS / SS / ALLOY (P11, P22, P91) | 230 | 2009.12 | CHILE | 240MW (240MW x 1Unit) |
211 | UAE SHUWEIHAT S2 | SAMSUNG C&T | ALLOY (P11, P22, P91) | 550 | 2009.12 | UAE | 1,500MW (750MW x 2Units) |
212 | North Bangkok | Mitsubishi Power (Hitachi) | CS / SS / ALLOY (P22, P91) | 329 | 2009.05 | THAILAND | 704MW (704MW x 1Unit) |
213 | GP1Z PHASE III | IHI | CS / SS / ALLOY (P11, P22, P91) | 4936 | 2009.04 | ALGERIA | - |
214 | QATALUM | DOOSAN | CS / SS / ALLOY (P22, P91) | 717 | 2009.01 | QATAR | 1,350MW (1Unit) |
215 | GUNSAN | DAEWOO E&C | CS / SS / ALLOY (P11, P22, P91) | 738 | 2009.01 | KOREA | 700MW (240MW x 3Units) |
216 | MUKHAIZNA (EXTERNAL/INTERNAL) | NEM | CS | 290 | 2008.11 | OMAN | 126MW (126MW x 1Unit) |
217 | Nueva Ventanas | POSCO E&C | CS / ALLOY (P11, P22, P91) | 260 | 2008.09 | CHILE | 240MW (240MW x 1Unit) |
218 | AFAM VI | DAEWOO E&C | CS / ALLOY (P11, P22) | 147 | 2007.10 | NIGERIA | 650MW (650MW x 1Unit) |
219 | Trimble County2 | DOOSAN | ALLOY (P12, P91) | 2007.08 | USA | 760MW (760MW x 1Unit) | |
220 | BORYONG #7/8 | DOOSAN | CS / ALLOY (P11, P22, P91) | 696 | 2007.07 | KOREA | 1,000MW (500MW x 2Units) |
221 | DANGJIN #7/8 | DOOSAN | CS / ALLOY (P11, P22, P91) | 696 | 2007.07 | KOREA | 1,000MW (500MW x 2Units) |
222 | HADONG #7/8 | DOOSAN | CS / ALLOY (P11, P22, P91) | 696 | 2007.07 | KOREA | 1,000MW (500MW x 2Units) |
223 | TAEAN #7/8 | DOOSAN | CS / ALLOY (P11, P22, P91) | 696 | 2007.07 | KOREA | 1,000MW (500MW x 2Units) |
224 | Sipat#1/2/3 integral"A/B" | DOOSAN | CS / ALLOY (P12, P91, P92) | 489 | 2007.02 | INDIA | 1320MW (660MW x 2Units) |
225 | BORYONG #7/8 | KOMIPO | CS / ALLOY (P11, P22, P91) Hanger & Supports 1,600sets / 380 tons | 1300 | 2007.02 | KOREA | 1,000MW (500MW x 2Units) |
226 | ECC | NEM | CS / ALLOY (P11, P22) | 90 | 2007.01 | SINGAPORE | 1Unit |
227 | YEONGHEUNG #3/4 | Mitsubishi Power (Hitachi) | CS / ALLOY (P11, P22, P91) | 250 | 2006.11 | KOREA | 1,740MW (870MW x 2Units) |
228 | HADONG #1/2 | DOOSAN | CS / ALLOY (P11, P22, P91) | 352 | 2004.06 | KOREA | 1,000MW (500MW x 2Units) |
229 | DANGJIN #5/6 "A" | DOOSAN | CS / ALLOY (P11, P22, P91) | 122 | 2003.09 | KOREA | 1,000MW (500MW x 2Units) |
230 | YEONGHEUNG #1/2 | KEPCO / SUNG CHANG | CS / ALLOY (P11, P22, P91) | 2500 | 2002.12 | KOREA | 1,600MW (800MW x 2Units) |
231 | BUSAN | DOOSAN | CS / ALLOY (P11, P22, P91) | 2002.05 | KOREA | 900MW (450MW x 2Units) | |
232 | YEONGNAM #2 | KEPCO / HYUNDAI | CS / ALLOY (P11, P12) | 80 | 2002.01 | KOREA | 200MW (200MW x 1Unit) |
233 | PULAU SERAYA | SIEMENS /SAMSUNG CORP. | CS / ALLOY (P11, P22, P91) | 212 | 2001.09 | SINGAPORE | 370MW (370MW x 1Unit) |
234 | BARIA | HEC | CS / SS / ALLOY (P22) | 207 | 2001.04 | VIETNAM | 250MW (1Unit) |
235 | JEBEL ALI "D"PHASEⅡ | HYUNDAI/ DE & WA | CS / ALLOY (P91) | 419 | 2001.02 | UAE | 397MW |
236 | TANIR BAVI | HYUNDAI & CONST / INDIA | CS / SS / ALLOY (P22) | 64 | 2001.02 | INDIA | 220MW (220MW x 1Unit) |
237 | BUSAN | DOOSAN | CS / ALLOY (P11, P22, P91) | 2001.01 | KOREA | 450MW (450MW x 1Unit) | |
238 | ATTAHADDY | HYUNDAI / LIBYA | ALLOY (P91) | 136 | 2000.11 | LIBYA | - |
239 | ULSAN FGD | DAEWOO / KEPCO | DUPLEX(UNS 31803) | 37 | 1997.07 | KOREA | 400MW (400MW x 1Unit) |
240 | DANGJIN #1 | HANJUNG / KEPCO | ALLOY (P22) | 30 | 1996.12 | KOREA | 200MW (200MW x 1Unit) |
241 | DANGJIN #1/2 | HANJUNG / KEPCO | ALLOY (P91) | 54 | 1996.12 | KOREA | 1,000MW (500MW x 2Units) |
242 | HADONG #3/4 | HANJUNG / KEPCO | ALLOY (P91) | 106 | 1996.12 | KOREA | 1,000MW (500MW x 2Units) |
243 | DONGHAE #2 | HANJUNG / KEPCO | ALLOY (P91) | 74 | 1996.11 | KOREA | 200MW (200MW x 1Unit) |
244 | HADONG #4 | HANJUNG / KEPCO | EN 15NiCuMoNb5 | 329 | 1996.11 | KOREA | 500MW (500MW x 1Unit) |
245 | DANGJIN #1/2 | HANJUNG / KEPCO | ALLOY (P22) | 20 | 1996.11 | KOREA | 1,000MW (500MW x 2Units) |
246 | DANGJIN #1/2 "A" | HANJUNG / KEPCO | EN 15NiCuMoNb5 | 266 | 1996.09 | KOREA | 1,000MW (500MW x 2Units) |
247 | HADONG #4 "A" | HANJUNG / KEPCO | ALLOY (P11, P12) | 133 | 1996.08 | KOREA | 500MW (500MW x 1Unit) |
248 | HADONG #4 "B" | HANJUNG / KEPCO | ALLOY (P11, P12) | 133 | 1996.08 | KOREA | 500MW (500MW x 1Unit) |
249 | SEO-INCHEON #3/4 | HANJUNG/ KEPCO | ALLOY (P22) | 60 | 1996.08 | KOREA | 300MW (150MW x 2Units) |
250 | HADONG #3/4 | HANJUNG / KEPCO | CS | 1996.07 | KOREA | 1,000MW (500MW x 2Units) | |
251 | DANGJIN #1/2 | HANJUNG / KEPCO | CS | 1996.07 | KOREA | 1,000MW (500MW x 2Units) | |
252 | HADONG #3 | HANJUNG / KEPCO | ALLOY (P11, P12) | 329 | 1996.07 | KOREA | 500MW (500MW x 1Unit) |
253 | HADONG #3/4 | HANJUNG / KEPCO | ALLOY (P22) | 20 | 1996.06 | KOREA | 1,000MW (500MW x 2Units) |
254 | HADONG #3 | HANJUNG / KEPCO | ALLOY (P11, P12) | 199 | 1996.06 | KOREA | 500MW (500MW x 1Unit) |
255 | HADONG #3/4 "B" | HANJUNG / KEPCO | EN x20CrMo12.1 | 398 | 1996.06 | KOREA | 1,000MW (500MW x 2Units) |
256 | DONGHAE #2 | HANJUNG / KEPCO | ALLOY (P22) | 66 | 1996.06 | KOREA | 200MW (200MW x 1Unit) |
257 | SAMCHEONPO #5 | HANJUNG / KEPCO | EN x20CrMo12.1 | 10 | 1996.05 | KOREA | 500MW (500MW x 1Unit) |
258 | HADONG #3 | HANJUNG / KEPCO | ALLOY (P11, P12) | 133 | 1996.05 | KOREA | 500MW (500MW x 1Unit) |
259 | SAMCHEONPO #6 | HANJUNG / KEPCO | ALLOY (P22) | 18 | 1996.04 | KOREA | 500MW (500MW x 1Unit) |
260 | SAMCHEONPO #5 | HANJUNG / KEPCO | EN x20CrMo12.1 | 133 | 1996.03 | KOREA | 500MW (500MW x 1Unit) |
261 | DANGJIN #1/2 "A" | HANJUNG / KEPCO | ALLOY (P91) | 280 | 1996.01 | KOREA | 1,000MW (500MW x 2Units) |
262 | DANGJIN #1/2 "B" | HANJUNG / KEPCO | ALLOY (P11, P12) | 398 | 1996.01 | KOREA | 1,000MW (500MW x 2Units) |
263 | DANGJIN #1/2 | HANJUNG / KEPCO | EN 15NiCuMoNb5 | 658 | 1996.01 | KOREA | 1,000MW (500MW x 2Units) |
264 | SAMCHEONPO #5/6 | HANJUNG / KEPCO | ALLOY (P22) | 20 | 1996.01 | KOREA | 1,000MW (500MW x 2Units) |
265 | SAMCHEONPO #6 "B" | HANJUNG / KEPCO | EN x20CrMo12.1 | 76 | 1996.01 | KOREA | 500MW (500MW x 1Unit) |
266 | HADONG #3/4 | HANJUNG / KEPCO | CS | 1996.01 | KOREA | 1,000MW (500MW x 2Units) | |
267 | DANGJIN #1/2 | HANJUNG / KEPCO | CS | 1996.01 | KOREA | 1,000MW (500MW x 2Units) | |
268 | HADONG #3/4 | HANJUNG / KEPCO | ALLOY (P91) | 54 | 1996.01 | KOREA | 1,000MW (500MW x 2Units) |
269 | SAMCHEONPO #5/6 | HANJUNG / KEPCO | ALLOY (P91) | 64 | 1995.12 | KOREA | 1,000MW (500MW x 2Units) |
270 | SAMCHEONPO #6 | HANJUNG / KEPCO | EN x20CrMo12.1 | 141 | 1995.12 | KOREA | 500MW (500MW x 1Unit) |
271 | SAMCHEONPO #5 | HANJUNG / KEPCO | EN x20CrMo12.1 | 199 | 1995.06 | KOREA | 500MW (500MW x 1Unit) |
272 | TAEAN #3 | HANJUNG / KEPCO | ALLOY (P22) | 25 | 1995.06 | KOREA | 500MW (500MW x 1Unit) |
273 | DONGHAE #1 | HANJUNG / KEPCO | ALLOY (P22) | 25 | 1995.06 | KOREA | 500MW (500MW x 1Unit) |
274 | SAMCHEONPO #6 | HANJUNG / KEPCO | ALLOY (P11, P12) | 133 | 1995.05 | KOREA | 500MW (500MW x 1Unit) |
275 | TAEAN #4 | HANJUNG / KEPCO | ALLOY (P11, P12) | 133 | 1995.04 | KOREA | 500MW (500MW x 1Unit) |
276 | TAEAN #4 | HANJUNG / KEPCO | ALLOY (P11, P12) | 329 | 1995.03 | KOREA | 500MW (500MW x 1Unit) |
277 | HADONG #1/2 | HANJUNG / KEPCO | ALLOY (P11, P12) | 398 | 1994.12 | KOREA | 1,000MW (500MW x 2Units) |
278 | TAEAN #3 | HANJUNG / KEPCO | ALLOY (P11, P12) | 329 | 1994.12 | KOREA | 500MW (500MW x 1Unit) |
279 | SEOCHON #1.2 | HANJUNG / KEPCO | CS / ALLOY (P11) | 300 | 1994.06 | KOREA | 400MW (200MW x 2Units) |